Walk-In Shower Remodel in Renton, WA

This Renton project replaced one shower in a primary bathroom and left the rest of the room alone. The old enclosure came out on day two, the new walls and floor were tiled within a week, and the shower was usable by April 14, 2023. A frameless glass door finished it in May. The jetted tub, vanity and floor beside it stayed as they were.

City
Renton, WA
Service
Shower remodel
Scope
Old shower removed to the studs, walls waterproofed, plank tile walls to the ceiling, hexagon tile floor, recessed niche, new valve trim, frameless glass door
Duration
About two weeks of work, April 3 to April 14, 2023, with the glass door fitted in May
Approximate investment
About $15,000
Materials
Light plank tile on the walls, hexagon mosaic floor, square drain, chrome fixtures, frameless glass door
Contractor
Volcano Builders, WA license VOLCABI792C6

Every project is priced in writing, line by line, for your home.

Finished walk-in shower with a frameless glass door, plank tile walls and a hexagon floor
The finished Renton shower behind its frameless glass door
Before

Before the build

Shower walls tiled in light gray plank tile with a recessed niche on the side wall
During: plank tile up to the ceiling, with the niche in the side wall
After

The finished shower

Finished walk-in shower with a frameless glass door, plank tile walls and a hexagon floor
The finished Renton shower behind its frameless glass door
Tiled walk-in shower with a tall niche, chrome shower head and hexagon floor
Renton shower: tall niche, chrome trim and the hexagon floor
New tiled shower beside an existing jetted tub in a primary bathroom
The new Renton shower next to the existing jetted tub

Know someone planning a project like this? Refer them: you get $500 cash or $1,500 credit, they get $500 off.

The project

How this Renton shower came together

The goal

The homeowners wanted a new walk-in shower without remodeling the whole bathroom. The jetted tub, the vanity and the floor tile around them were staying, so the work had to stop at the shower walls.

The challenge

Replacing a shower in a finished room means working next to surfaces that are meant to survive. The old enclosure had to come out cleanly, the new waterproofing had to tie into the same opening, and the new tile had to meet the existing floor and wall paint without patching beyond the shower.

The solution

Demolition was done by April 4. The alcove was taken down to the studs, rebuilt with waterproof board and a sloped pan, and the seams sealed before any tile went up. A light hexagon mosaic went on the floor around a square drain, and light gray plank tile runs from the curb to the ceiling, with a tall recessed niche on the side wall for bottles. Chrome valve trim and a shower head went on last. The glass was measured after the tile was finished, and a frameless hinged door was installed in May.

The result

The tile was finished by April 10 and the shower was complete on April 14, 2023, about two weeks after the start. The new shower reads as part of the room: the tub, the vanity and the floor around it are unchanged, and only the shower itself is new.

Keep reading
Questions

Questions about this project

Can you replace just the shower and keep the rest of the bathroom?

Yes. On this Renton job only the shower was rebuilt. The jetted tub, vanity and floor beside it stayed in place, and the new tile and glass were fitted to the existing opening.

Why was the glass door installed weeks after the tile?

Frameless glass is cut to the finished tile, so it is measured once the walls and curb are done. Here the tile was finished on April 10, and the door was ordered and fitted in May.

How much did this project cost?

About $15,000. It took about two weeks, from April 3 to April 14, 2023, with the glass door fitted in May. Every project is priced in writing, line by line, for your home.

How do I get a price for a shower remodel like this one?

Book a consultation. We look at the shower and what has to stay around it, and send a written, itemized price before work starts. Our guide Cost of a Bathroom Remodel in the Greater Seattle Area explains what moves the number.

Next steps

Before you book

Volcano Builders team member holding a phone showing the Google Business listing, Built Without Compromise

Book your shower consultation

Four quick steps. Tell us about your project and we’ll reach out to discuss it and see if we’re the right fit.

What is your project?