Glass Subway Tile Bathroom Remodel in Seattle, WA

In this Seattle bathroom we rebuilt the shower and every wall around it in about 9 weeks, from November 2022 to January 2023. The shower now has white glass subway tile, a black polished pebble floor with a linear drain and a sliding framed glass door. When demolition showed the walls were double layered drywall, we stripped them, hung new board and repainted the room, then put the existing dark wood vanity back in place.

City
Seattle, WA
Service
Bathroom remodel
Scope
Shower rebuilt and retiled, walls stripped and redone in new drywall, room primed and painted, new floor tile, existing vanity removed and reinstalled
Duration
About 9 weeks, November 18, 2022 to January 17, 2023
Approximate investment
About $35,000
Materials
White glass subway tile, black round polished pebble shower floor, linear drain, sliding framed shower door, marble-look floor tile
Contractor
Volcano Builders, WA license VOLCABI792C6

Every project is priced in writing, line by line, for your home.

Long narrow bathroom with a dark wood vanity and dark stone top leading to a glass-enclosed subway tile shower
The finished Seattle bathroom, looking past the vanity to the shower
After

The finished bathroom

Long narrow bathroom with a dark wood vanity and dark stone top leading to a glass-enclosed subway tile shower
The finished Seattle bathroom, looking past the vanity to the shower
Bathroom with a skylight above a lit mirror cabinet, dark wood vanity and marble-look floor tile
A skylight and lit mirror cabinet over the reinstalled vanity
Dark stone vanity top with an undermount sink and the shower at the end of the room
The stone-topped vanity, with the shower beyond
Dark wood shaker vanity with chrome pulls under a mirrored medicine cabinet
Dark wood vanity drawers under the mirror cabinet
Sliding framed glass shower door in front of white subway tile and a black pebble floor
The sliding framed door on the new shower
Walk-in shower with white glass subway tile walls, a recessed niche and a black pebble tile floor
White glass subway tile and a black pebble floor in the Seattle shower
Shower wall with a handheld shower on a slide bar and a linear drain in the pebble floor
Handheld shower on a slide bar, with a linear drain below
Side wall of the shower in white glass subway tile with a handheld shower and valve
The long side wall of glass subway tile
Shower corner with a tiled niche and a small window set into the subway tile wall
A tiled niche beside the shower window

Know someone planning a project like this? Refer them: you get $500 cash or $1,500 credit, they get $500 off.

Video

This bathroom on video

Video thumbnail: this Seattle bathroom with glass subway tile
Video of this Seattle bathroom with glass subway tile. 27 seconds.
The project

How this Seattle bathroom came together

The goal

The bathroom is long and narrow, with the shower at the far end, a skylight overhead and a dark wood vanity with a dark stone top along one wall. The scope was a new shower and fresh walls, keeping the existing vanity.

The challenge

Once demolition began, the walls turned out to be covered in two layers of drywall. That was not something a patch could fix, and the vanity sat against one of those walls. Both had to be dealt with before the shower could be tiled.

The solution

We took the vanity out and set it aside, stripped the double drywall, hung new board and taped and textured it to match the rest of the home, then primed and painted the whole room. In the shower, the alcove was waterproofed and tiled in white glass subway tile laid in long horizontal runs, with a recessed niche on the back wall and a handheld shower on a slide bar. The floor is black round polished pebble tile sloped to a linear drain, and a sliding framed glass door closes it in. Marble-look tile went down across the main floor, and the vanity went back exactly where it was, under a lit mirror cabinet.

The result

Work began on November 18, 2022 and the project was complete on January 17, 2023, about 9 weeks. The glass tile catches the light from the skylight, the black pebble floor gives the white shower a clear base, and the reinstalled dark wood vanity now sits against straight, freshly painted walls.

Keep reading
Questions

Questions about this project

What happens if you find a problem behind the walls during a bathroom remodel?

We stop, show you what we found and price the fix in writing before doing it. Here the walls were double layered drywall, so a change order covered stripping them, new drywall, texture, paint, and removing and reinstalling the vanity.

Can I keep my existing vanity in a bathroom remodel?

Often, yes. In this Seattle bathroom the dark wood vanity and its stone top were taken out, stored while the walls were rebuilt, and reinstalled in the same spot.

How much did this project cost?

About $35,000. It took about 9 weeks, from November 18, 2022 to January 17, 2023. Every project is priced in writing, line by line, for your home.

How do I get a price for a bathroom remodel like this one?

Book a consultation. We look at the room, talk through the shower, tile and anything you want to keep, and send a written, itemized price before work starts. For what moves the price of a bathroom, read Cost of a Bathroom Remodel in the Greater Seattle Area.

Next steps

Before you book

Volcano Builders team member holding a phone showing the Google Business listing, Built Without Compromise

Book your bathroom consultation

Four quick steps. Tell us about your project and we’ll reach out to discuss it and see if we’re the right fit.

What is your project?